Durazno Water Treatment Plant
OSE
Durazno, Uruguay
Construction of a drinking water treatment plant and ancillary works.
This work ensures the supply of drinking water of the required quality and in the necessary quantity to supply the city of Durazno.
Main project components:
- Executive Project
- Change of supply pumps at the existing intake.
- Construction of adductor pipeline to the new plant.
- Construction of the facilities for the new drinking water plant, elevator pump room and reserve tank.
- Construction of a pressure pipeline to the city's elevated reservoir.
- Construction of new offices for the technical area of Durazno.
- Telecontrol, SCADA and Communications System.
- Auxiliary services (AC and DC).
Water treatment plant components:
- Fast online mixing.
- Mechanical and hydraulic flocculators.
- High rate settlers.
- Two-layer sand-anthracite and granular carbon filters.
- Chlorine contact chamber and filtered water tank
- Lift pump room
- Facilities for storage, preparation and dosing of chemical products
- Treatment line consisting of:
- Filter effluent settler
- Sludge thickener
- Dehydration unit