Turbogenerator

Client:

MONTES DEL PLATA

Location:

Colonia, Uruguay

Status:

The project includes concrete and masonry work for the turbogenerator building within the plant.

They are performed:
- Construction of 3,550 m2 of block walls.
- 23,000 m2 of paintings on walls and ceilings.
- 7,400 m2 of floor finishing including epoxy paint.
- 1,000 m2 of roof waterproofing.
- 3,000 kgs of supply and installation of stairs and handrails.
- Supply and installation of different types of fireproof openings.
- 8,500 m2 of asphalt laying.