Civil Association La Esperanza
CITY HALL OF MONTEVIDEO
Montevideo, Uruguay
Infrastructure, sanitation, rainwater drainage, drinking water, roads, electricity, public lighting and construction of 35 housing units for relocation.
Roads: 13,027m3 of soil movement, 8,685m3 of sand replacement, 10,531m2 of asphalt paving equivalent to 1293 tons, 2913ml of curb and gutter and 269 m2 of concrete speed bump.
- Sewage: 1,885ml of PVC pipe with a diameter of 200mm, connecting to the existing sewage system in the area. Execution of 150 house connections with a nominal diameter of 160 mm.
- Drinking water: 2,174ml of HDPE pipe with diameters of 75 and 110mm. Execution of 200 connections
- Pluvial: 100ml of 1500mm reinforced concrete pipe and 330ml of 800mm.
- Electricity: Electricity corresponds to 200 home connections.
- Housing: 35 housing units and a neighborhood center with an office are being built. The resistant structure is made of reinforced concrete pillars and beams. The cover is made of 100 mm isopanel.
- Siding: Exterior cladding is field brick and block; interior walls are bolseted.