Spray Tower III

Client:

CONAPROLE

Location:

San José, Uruguay.

Status:

The project includes the construction of the third Spray building at Conaprole's plant in the Villa Rodríguez Industrial Complex, department of San José.

It consists of the construction of a reinforced concrete structure, installation of plaster partition walls and ceilings, masonry walls, and a sheet metal façade enclosure.

It involves the installation of different items such as: industrial sanitation, fire detection and firefighting, HVAC, metal structures of different types (stairs, platforms, equipment bases, raised floors), aluminum, painting, elevator and freight elevator, among others.

The building must meet high quality and hygiene standards. It consists of 11 floors divided into a Spray tower, an Evaporator tower and an annex room with a substation and a machine room.

They are performed:
- 3,800 m3 of reinforced concrete
- 4,350 m2 of building constructions
- 9,700 m2 of panels